For the week of: 9/23/2024
What to expect:
– The first concrete pour is scheduled for 9/24/24. The pour will consist of the retaining wall footing along the east edge of the property and concrete fill beneath the building’s electrical room.
– Building footing subgrade prep and formwork to begin in the next week.
– Stormwater system installation is scheduled to begin as early as next week, starting with trenching.
Major milestones on the project:
– Under slab plumbing rough-in completed.
– Under slab electrical rough-in completed.
– Retaining wall footing formwork and rebar completed and inspected.
About the new Health Center and Pharmacy
– The new facility in Wheeler will replace the existing Nehalem Bay Health Center and Pharmacy and provide more than 16,000 square feet of space accommodating 15 exam and treatment rooms, a modern pharmacy, a dental suite, x-ray, behavior
health unit and a community room.
– The project is being developed by the Nehalem Bay Health District and the District will own the building.
– Medical personnel and services will be provided by the local non-profit Nehalem Bay Health Center that will lease the new facility from the District.
Have questions?
• Email the Health District at: info@nehalembayhd.org
• Call: Kevin McMurry: 503-753-1185, Jake Werger: 971-221-5958
or Marc Johnson: 208-866-6864
• Visit the District website: www.nehalembayhd.org