News from the Nehalem Bay Health District

Submitted By: marc@nehalembayhd.org – Click to email about this post
Nehalem Bay Health Center and Pharmacy Update

For the week of: 12/16/2024

What to expect this week:
– First floor perimeter and interior wall framing.
– Second floor joist framing.
– Retaining wall footing at generator and transformer area to be formed and poured.

Major milestones on the project:
– Building structural steel has been installed.
– Carpentry crews mobilized to the site and delivered the lumber donated by Hampton Lumber.
– Excavation and subgrade prep at generator

About the new Health Center and Pharmacy:
– The new Health Center and Pharmacy project is a direct result of the five-year strategic plan the Health District adopted in 2019. That plan, now being updated, identified enhanced local health care as a top community priority.
– The new Health Center will triple the size of the current facility (the former Rinehart Clinic) and have space to accommodate specialty services, including dental and x-ray. 
– The new Health Center will have 15 exam and procedure rooms, a major upgrade from the existing facility.
– The new Health Center has been designed with energy efficiency and sustainability in mind and will include a solar array, an emergency generator and a variety of energy saving features. 

Have questions?
– Email the Health District at: info@nehalembayhd.org
– Call: Kevin McMurry: 503-753-1185, Jake Werger: 971-221-5958 or Marc Johnson: 208-866-6864
– Visit the District website: www.nehalembayhd.org