For the week of: 1/20/2025
What to expect this week:
• Second floor wall framing to be completed
• HVAC rough-in at low roof area to begin
• Fire sprinkler rough-in at low roof area to begin
Major milestones on the project:
• Second floor joists and sheathing completed
• Low roof area dried in
• Low roof area weather resistant barrier installed
About the new Health Center and Pharmacy
• The new Health Center and Pharmacy project is a direct result of the five-year strategic plan the Health District adopted in 2019. That plan, now being updated,identified enhanced local health care as a top community priority. The new Health Center will triple the size of the current facility (the former Rinehart Clinic) and have space to accommodate specialty services, including dental and x-ray.
• The new Health Center will have 15 exam and procedure rooms, a major upgrade from the existing facility.
• The new Health Center has been designed with energy efficiency and sustainability in mind and will include a solar array, an emergency generator and a variety of energy saving features.
Have questions?
• Email the Health District at: info@nehalembayhd.org
• Call: Kevin McMurry: 503-753-1185, Jake Werger: 971-221-5958 or Marc Johnson: 208-866-6864
• Visit the District website: www.nehalembayhd.org